a create table time schedule and graph table curve S which is related to my post about irrigation channel a few days ago.
day I would like to continue on the irrigation channel work I have postped in a few days that have been leawt, because in every work the channel activity I have described in the last few days or in any job is not necessarily about civil engineering, but also in any work on other engineering sciences,
here I will make a table and graph of the S curve for an irrigation channel work I have described in some posts ago, this channel with a length of P = 100 meters and with the budget plan cost, and the volume for this channel also I have explained in some posts that have been passed,
this is the type of channel work with volume and total cost budget results:
| Job type description | Volume | the amount of costs |
|---|---|---|
| 1. for field cleaning work | 150 M² | 1,575.000,00,- |
| 2. for soil works excavation | 121,125 M³ | 1,271.982,00,- |
| 3. for concrete casting work K.225Mpa | 47.10 M³ | 59,103.576,00,- |
| 4. for the job of Plastering wall channel1SP : 2PP | 160 M² | 9,313.120,00,- |
below I attach a few tables namely Table Schedule Time schedule and table Graph of the S Curve for the work of irrigation channels.
this is a table to know about the work activity plan, this is the beginning of an activity to be carried out the work with the existence of this implementation schedule all the target activity for the job and the time of work will be right with this table, with us easily control the implementation of this work.
Graph of the curve S
- a.Table of activity
this table shows the percentage rate per day for work activities that are being done. this table has not seen clear graph of curve S, but only number of daily activity activity.
- the calculation phase of field cleaning
- stages of calculation of soil excavation on channel work
- Making 1 m3 of Quality Concrete f'c = 19.3 Mpa (K 225),Slump (12 ± 2) cm, w / c = 0.58
- Work Plastering Water factor a cement 1SP: 2PP 1 m2 Thickness 15 mm
- Administration
this is the same as it is, I cut it so that it looks clearly the percentage lob for this irrigation work, and I add a little steemit logo beside it.
this is the percentage table of work done in the work or done, the table shows the garfik curve S by symbolizing the process of a job in accordance with the planned before the implementation of the work,
this is what I can explain in this table then the finished all the explanation of the problem about this irrigation channel in each of my posting this.
thank you for my friends who explore the science of engineering and for those who have seen my work, apologize for any deficiencies both in terms of content and writing.
for more details, if you want to understand more and interrelate with table schedule of execution and Table Curve S this, then please see at source my link below
https://steemit.com/engineering/@aguess/simple-irrigation-channels-with-volumes-i-have-calculated-with-the-facts-on-the-job-field
https://steemit.com/science/@aguess/analysis-of-volume-calculation-and-budget-plan-at-irrigation-channel-work