Hot Strip Mill Production Process have Four Steps.
1)Furnace 2) Roughing Mill 3)Tandem Mill 4)Down Coiler.
In Furnace Mild Still/ SS Slab is making Hot around 1200°c Temperature and send it to Roughing Mill for Further Process through Roller Table.
In Roughmill Mill we Removed the Scale from the slab by High pressure Water Descaling Process and Reduced the Slab Thickness By Rolling the Slab through it two three time and send it Tandem Mill through Roller Table for Further Process.
Down Coiler Wrapped the hot strip into the coil formation.